An existing, high-traffic access road became extremely muddy, causing heavy machinery to slide off the roads. The area was in need of soil stabilization techniques for roadway construction to allow trucks to come in and out before the first snowfall.
Preparation
This 33,000 sq ft area required immediate ground stabilization, with little time to prepare in muddy conditions.
Installation
Ecoraster E50 porous pavement was chosen for ground reinforcement. Fill was poured on top for additional traction and to support the high frequency of trucks. This access road installation needed to be carried out in a very short period of time between days of wintry weather and the warm, wet days of spring.
After
In just a matter of days, Ecoraster’s mud management grid helped transform this muddy area into a safe and stable access road to support heavy transport trucks and machinery. The concern for continued safety has been resolved and the group has been pleased with the success of the Ecoraster paver grid holding up to harsh weather.